Maharashtra Forest Department Suspends Adani's Tarali Project Work
The Maharashtra Forest Department has issued an immediate stop-work notice for the 1,500 MW Tarali Pumped Storage Project in Satara district, being developed by Adani Green Energy Limited. This action comes due to the absence of necessary prior approval from the National Board for Wildlife (NBWL), as reported by The Indian Express.
The issuance of the stop-work notice raises significant questions regarding how construction was permitted to continue without the requisite wildlife clearance. Additionally, the department had accepted a substantial revision to the project's estimated costs, including a dramatic reduction in the proposed conservation levy from ₹227 crore to just ₹2.27 crore.
On November 13, the Satara forest administration delivered the stop-work directive shortly after The Indian Express highlighted the company's revised cost acceptance from ₹5,675 crore to ₹56.75 crore. The decrease in the conservation contribution has been a focal point of scrutiny.
During an inspection of the site, it was observed that construction had commenced without the mandatory approval from the NBWL, due to the project's location within the Eco-Sensitive Zone (ESZ) of the Sahyadri Tiger Reserve. The notice conveyed the seriousness of this violation, stating, "Upon inspection carried out in connection with the Tarali PSP, it has been observed that you have commenced actual execution of the project without obtaining the mandatory prior approval of the NBWL. This matter is extremely serious and violates the provisions of the prevailing Forest and Wildlife Acts."
The forest department has requested a written response from Adani Green Energy within three days, seeking clarification on the authority under which construction began without NBWL approval. The notice also demands statutory clearance documents and permissions related to tree felling at the site, warning of potential legal actions should a satisfactory response not be provided.
In March 2026, M. Srinivas Reddy, Maharashtra’s Principal Chief Conservator of Forests (Wildlife), instructed the company to deposit ₹227 crore for wildlife conservation and submit an affidavit agreeing to adhere to 14 additional conditions before the proposal could be advanced to the NBWL. However, after the company submitted a notarised affidavit on September 8 to revise the project cost, Reddy informed them on October 12 that the lower estimate had been accepted.
Following this acceptance, the company was directed to immediately deposit ₹56.75 lakh, representing 1% of the new project cost, with an additional 3% to be paid after obtaining NBWL approval. While the company fulfilled the immediate financial requirement, this did not equate to gaining wildlife clearance.
The acceptance of the revised project estimate, issued by Reddy, and the subsequent stop-work notice from the Satara forest administration may reflect a communication breakdown between the two offices concerning the clearance status.
In a statement released on November 16, Adani Green Energy maintained that none of the project area falls within a declared Protected Area and insisted no forest land was involved. The company claimed to have received a no-forest-land certificate on January 23, 2024, along with environmental clearance on February 11, 2025, and Consent to Establish (CTE) on April 7, 2025. They assert that construction only began after obtaining the necessary approvals.
The wildlife clearance process, according to Adani, was initiated as part of fulfilling environmental clearance compliance requirements. They indicated that a proposal for preliminary survey activities was submitted in January 2025 and gained recommendation from the State Board for Wildlife (SBWL). Adani has reportedly submitted a proposal to the NBWL seeking clearance for the project, which is still under consideration.
The scrutiny of the cost revision was stimulated by complaints from Rohan Bhate, an Honorary Wildlife Warden of Satara district, who filed grievances on October 30 through several government portals, claiming inaccuracies in the reported project costs. Following this, the Union Ministry of Environment, Forest and Climate Change directed the state forest department to conduct a swift investigation into the matter, as stated by The Indian Express.
The Tarali project is designed on the Tarali dam reservoir and spans 150.74 hectares of non-forest land across the villages of Nivade, Tondoshi, Kalambe, and Jalu in Patan taluka of Satara district.
Kashmir Commander Lateef Bhat Engaged in Standoff in Kulgam
Modi Promotes E-Visas for ASEAN Tourists at Manila Summit
BJP Responds to Rahul Gandhi's 'Dead Economy' Comment with Growth Data
BSF Jawan Detained by Bangladesh Border Force: Repatriation Efforts Begin